ERP timelines slip for predictable reasons: late data, unclear requirements, slow decisions and integrations discovered late. A realistic plan names those risks and builds decision points around them.
This guide gives typical phase durations by company size and the milestones worth tracking, without pretending every project follows the same calendar.
Typical durations
The ranges below assume a standard mid-market scope with a committed business team and a competent partner. Add 30–50% for multi-site, regulated or heavily integrated projects.
| Company size | Discovery & design | Build & test | Cutover & hypercare | Total |
|---|---|---|---|---|
| 25–50 users | 2–4 weeks | 6–10 weeks | 2–4 weeks | 3–5 months |
| 50–250 users | 4–8 weeks | 3–5 months | 4–6 weeks | 5–8 months |
| 250–1,000 users | 6–12 weeks | 5–9 months | 6–10 weeks | 8–14 months |
| 1,000+ users | 3–6 months | 9–18 months | 2–4 months | 14–24 months |
The milestones that matter
Percentage complete is a poor predictor of go-live. Use evidence-based milestones instead: signed process design, clean data load, passing integration tests, completed mock cutover and business sign-off.
- Requirements signed off by process owners
- Fit-gap decisions closed with cost and owner
- Master data cleansed and validated
- End-to-end integration tests passed
- User acceptance testing signed off
- Two mock cutovers completed within window
- Go/no-go decision with named decision-maker
Why projects slip
The most common cause is not partner performance. It is unavailable business experts. If the people who understand the process are too busy to attend design workshops, the partner guesses and rework follows.
The second is late data. Cleansing always takes longer than planned, especially in companies that have grown through acquisition.
Plan hypercare properly
Hypercare is not a vague period of extra support. Define its length, staffing, issue severity levels, response times and exit criteria. Two to six weeks is typical.
Track ticket volume and closure rate weekly. If critical issues are still open at the end of hypercare, extend it rather than pretending the project is done.
When to delay go-live
Delay if critical data is not loaded, a core integration is unproven, key users are not trained or the first close cannot be simulated. A delay measured in weeks is cheaper than a failed month-end.
FAQ
Common questions
How long does a mid-market ERP implementation take?
Most mid-market implementations take 5–8 months from kickoff to go-live, with another 4–6 weeks of hypercare. Complex multi-site projects take 9–14 months.
Can ERP go live in three months?
Yes for a small, standard, single-entity deployment with clean data and limited integrations. It is unrealistic for multi-site manufacturing or anything requiring significant customisation.
What is the biggest cause of ERP delays?
Business expert availability, followed by data quality and late integration discovery. Technology issues are rarely the primary cause.